I made the layout ride for a 10k today, but will have to return on another day to do the verification ride. The tool won't let me enter my post calibration ride without completing the verification ride. I feel I already know the answer, use the LDE option, but there is no category for "Course measured on two different days" Did I miss something in training?
Course Measurements on two different days.
Correct, the LDE process is the appropriate routing for a course measured by the same measurer on different days.
Because a pre/post calibration is required for each day's ride, it is not (yet) subject to the main processing flow.
A couple courses have been received with this scenario and hence have been added to the list of tasks for further development.
Thanks for sharing this on the Forum